0 votes
1 view
by
What is L1 L2 L3 schedule?

1 Answer

0 votes
by
L1 schedules represent key milestones and events agreed upon by the client and contractor using a list, summary, or bar chart format. L2 schedules include critical network activities and senior management milestones. L3 schedules provide the lowest level of detail needed to complete the project through job completion.
...